Part 2 (50 Marks) : Select 5 of 6 Questions Question 1: (10 Marks) What are the processes defined in AS/NZS ISO 9001:2000 in making up a quality management system? Demonstrate these processes and explain how these processes link with a construction-related organisation. (Use the organisation from your team assignment.) Establish – goal, mission and value, process, stakeholders’ benefits Document Implement and Maintain Continually Improve Question 2 : (10 Marks) You are required to manage a construction of an underground reinforced concrete tank for rainwater retention. The client requires the construction to be done with high quality control so that the construction will not damage the existing foundation. The client also wants the construction to be completed in 2 months. Write the document control and approval process for the construction from commencement to completion. Document Procedure Approval process – Write diagram for approval process who needs to submit and who needs to approve. Review and update and re-approve Identify any changes and update current status of the document Ensure relevant versions of document are being use Identify the source of documents and ensure distribution control Prevent unintended use of obsolete documents Question 3 : (10 Marks) Suppose you are a quality engineer for a construction company that has three separate management systems: quality (ISO 9000), environmental (ISO 14000), and safety and health. From management system audit, it was found that a number of procedures established for management of these systems are in conflict and there are semi-formal systems in place that are difficult to implement. 11868 CE Quality Control 463 Semester ***, 2008 Name Student number 1 CE Quality Control 464, Semester 2 – 2008 Final Exam – Marking Scheme Question 1 Answer the following questions and explain the reasons of your answers. a) Describe in your own words your understanding about Quality Management System (QMS), from drafting to implementing. (5 marks) Based on “Plan-Do-Check-Act” • Drafting – planning to establish the system for quality management, set up QMS approach, establish goal and objectives, define stakeholders and clients, and scope, etc. • Implementing – develop work process, assign responsibilities, document and maintain, measure and monitor, then continue to improve b) With the requirements in ISO9001, who should be responsible and involved in setting up the QMS of an organisation? (4 marks) • Top management, all staff and stakeholders c) How to demonstrate the support of the top management of an organisation in order to achieve the desired quality objectives? (3 marks) • Establish and promote organisation policy for quality • Set up a system to demonstrate that the support in providing necessary resources to fulfil customer’s needs and expectations • Make decision and take actions for improvement d) What are the benefits of QMS? (3 marks) • Maintain business • Continue growth of business • Customer satisfaction Question 2 In planning a construction project in a remote site, propose a management approach that will lead to a successful completion of the project. (10 marks) Answer is to have “QMS” 1. Set up quality goal 2. set up organisation chart of site staff 3. identify stakeholders 4. define roles and responsibilities 5. set up infrastructure for site staff and plan for roaster duties to optimise the work on site, Infrastructures include offices, accommodation camp, warehouses, tools and 11868 CE Quality Control 463 Semester ***, 2008 Name Student number 2 equipment planning, health and safety issues, environmental issues, regulatory issues that relate to staff requirements to do site work, etc. 6. define and setup work process (use process-based approach as recommended in ISO9001-2000) 7. set up resource management system needed for the remote site 8. set up communication system and process for client approval 9. determine method to measure effectiveness and efficiency of the processes 10. set up control process to prevent non-conformities in terms of material specification, delivery method, testing measures to be done before and after deliveries to scan the first-round of nonconformities. 11. establish and apply process for continual improvement 12. establish a process for variation work orders and claims submission 13. keep track records of on and off site activities relating to the project 14. set up a document control system for an efficient transfer of the information necessary to execute the work in a timely manner 15. select the Project manager who has “8 management principles” quality, or be one. Question 3 During the construction of a building, the client has initiated the idea to enlarge a part of the building. The client has asked you, as the Project Manager, to propose a design and build solution. a) Describe a customer-related process for this work (5 marks) • Demand creation Customer requirements (determine, review and communicate) i.e., a design and build construction extension • Demand fulfilment Design phase - develop design management work process, document control and approval process, value-added process before final approval. Construction phase – contact suppliers, develop construction methods (planning for resources and Gantt chart), measuring and monitoring system (site supervision), documentation system and approval process (planning together in Gantt chart when and which document needs to be approved before any construction can commence). b) What needs to be done to avoid future disputes with regards to time, cost, and quality of the project?